Flood Control Projects

Monitoring and evaluation of ongoing and completed flood control projects

Project Image

Construction of Abo-Abo River Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 200 B/S Upstream, Barangay Abo-Abo, Sofronio Española, Palawan

Abo-Abo, Sofronio Española
Completed
Contractor: CUTTING EDGE BUILDERS AND TRADING, INC.
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 24499265.29
Duration: 15-Feb-23 - 19-Jul-23
4.0 (3)
Project Image

Construction of Abongan CIS Drainage Canal, Taytay, Palawan

Abongan, Taytay
Completed
Contractor: REINASTAR TRADING AND CONSTRUCTION SUPPLY
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 19598517.10
Duration: 14-Feb-24 - 28-Oct-24
5.0 (1)
Project Image

Construction of Aborlan River Waterway, (Downstream Leftside) Aborlan, Palawan

Tagpait, Aborlan
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 154398410.80
Duration: 2-Mar-24 - 5-Dec-24
2.0 (1)
Project Image

Construction of Aborlan River Waterway, Puerto Princesa South Road, Aborlan, Palawan

Gogognan, Aborlan
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 120268876.00
Duration: 11-Mar-23 - 10-Dec-23
2.0 (2)
Project Image

Construction of Aramaywan River Flood Control Structure, Aramaywan, Quezon, Palawan

Aramaywan, Quezon
Completed
Contractor: RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 29303558.24
Duration: 14-Feb-24 - 27-Jul-24
3.7 (3)
Project Image

Construction of Babuyan River Flood Control Strucure Downstream (LS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: G. BANZ BUILDERS CORP.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17029313.08
Duration: 23-Feb-24 - 24-Jun-24
0.0 (0)
Project Image

Construction of Babuyan River Flood Control Strucure Downstream (RS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: AZARRAGA CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17961569.07
Duration: 15-Feb-24 - 23-May-24
0.0 (0)
Project Image

Construction of Babuyan River Flood Control Strucure Upstream (LS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: F.F. GALANG CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 16802607.63
Duration: 23-Feb-24 - 24-Jul-24
0.0 (0)
Project Image

Construction of Babuyan River Flood Control Strucure Upstream (RS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: PANAAD CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 18334889.53
Duration: 15-Feb-24 - 17-Jul-24
0.0 (0)
Project Image

Construction of Barong-barong Flood Control Structure, Sta. 0+500 - Sta. 0+745, Brooke's Point, Palawan

Barong-barong, Brooke'S Point
Completed
Contractor: M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 11674127.13
Duration: 25-May-22 - 31-Jul-23
0.0 (0)
Project Image

Construction of Batang Batang River Flood Control Structure, Sta 0 + 200 - Sta. 0 + 900 L/S Downstream, Barangay Batang-Batang, Narra, Palawan

Batang-Batang, Narra
Completed
Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY)
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 50662496.45
Duration: 20-Feb-23 - 22-Dec-23
0.0 (0)
Project Image

Construction of Batang-batang River Flood Control Structure, Narra, Palawan

Batang-batang, Narra
Completed
Contractor: ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 53004257.50
Duration: 14-Feb-24 - 16-Sep-24
0.0 (0)
Project Image

Construction of Bato Bridge Flood Control Structure, Taytay, Palawan

Bato, Taytay
Completed
Contractor: MAC BUILDERS CIVIL ENGINEERING CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 9064029.80
Duration: 15-Mar-23 - 23-Oct-23
0.0 (0)
Project Image

Construction of Box Culvert in Sitios Sarimog and Pulangi, Latud, Rizal, Palawan

Latud, Rizal (Marcos)
Completed
Contractor: RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 9652747.12
Duration: 15-Feb-23 - 7-Oct-24
0.0 (0)
Project Image

Construction of Brooke's Point Shore Protection and Causeway Development, District I, Palawan

Poblacion I, Brooke'S Point
Completed
Contractor: MARCBILT CONSTRUCTION, INC.
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 45816740.98
Duration: 13-Apr-23 - 30-Sep-23
0.0 (0)
Project Image

Construction of Buluang Bridge I Flood Control Structure, Sta. 0 + 044.64 - Sta. 0 + 095.00 (UPSTREAM - BK.I), Sta. 0 + 000 - Sta. 0 + 095.00 (UPSTREAM - BK. II), Sta. 0 + 000.00 - Sta. 0 + 026.00 (DOWNSTREASM - BK. II), Busuanga, Palawan

Buluang, Busuanga
Completed
Contractor: MAC BUILDERS CIVIL ENGINEERING CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 8884656.00
Duration: 18-Apr-23 - 11-Aug-23
0.0 (0)
Project Image

Construction of Cabuluan River Flood Structure, barangay Calategas, Narra, Palawan

Calategas, Narra
Completed
Contractor: ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 192997354.30
Duration: 13-Apr-23 - 20-May-24
0.0 (0)
Project Image

Construction of Colby River Flood Control Structure, Rizal, Palawan

Taburi, Rizal (Marcos)
Completed
Contractor: SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 53072829.34
Duration: 14-Feb-24 - 15-Nov-24
0.0 (0)
Project Image

Construction of Colby River Flood Control Structure, Sta. 0 + 620 - Sta. 0 + 820 R/S Upstream, Barangay Taburi, Rizal, Palawan

Taburi, Rizal (Marcos)
Completed
Contractor: SAMURAI CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 19599689.79
Duration: 3-May-23 - 15-Dec-23
0.0 (0)
Project Image

Construction of Culasian Flood Control Structure, Sta. 0 + 082 - Sta. 0 + 162 R/S Downstream, Barangay Culasian, Rizal, Palawan

Culasian, Rizal (Marcos)
Completed
Contractor: F A M E CONSTRUCTION TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 9701996.20
Duration: 15-Feb-23 - 28-May-23
0.0 (0)
Project Image

Construction of Culasian River Flood Control Structure, Sta. 0+000 - Sta. 0+082, Rizal, Palawan

Culasian, Rizal (Marcos)
Completed
Contractor: AFG CONSTRUCTION CORPORATION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 9653000.00
Duration: 25-May-22 - 22-Apr-23
0.0 (0)
Project Image

Construction of Drainage Structure, Barangay San Miguel, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: SMMILEY BUILDERS AND TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 4900000.00
Duration: 15-Feb-23 - 27-Sep-23
0.0 (0)
Project Image

Construction of Drainage System along Barangay Maligaya, City of Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: F.F. GALANG CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 4851100.32
Duration: 10-Feb-22 - 5-Jul-22
0.0 (0)
Project Image

Construction of Drainage System, Tumarbong, Roxas, Palawan

Tumarbong, Roxas
Completed
Contractor: AFG CONSTRUCTION CORPORATION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 4514354.14
Duration: 30-Mar-23 - 29-Jun-23
0.0 (0)
Project Image

Construction of Flood Control Structure along Apurawan River Downstream (L/S), Aborlan, Palawan

Aporawan, Aborlan
Completed
Contractor: G. BANZ BUILDERS CORP.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369994.74
Duration: 7-Mar-24 - 24-Jun-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Apurawan River Downstream (R/S), Aborlan, Palawan

Aporawan, Aborlan
Completed
Contractor: PANAAD CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 14882574.20
Duration: 23-Feb-24 - 18-Jul-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Apurawan River Upstream (L/S), Aborlan, Palawan

Aporawan, Aborlan
Completed
Contractor: RITCHE-NATHALIE DEVELOPMENT CORPORATION (FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN. MERCHANDISE)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 16240699.93
Duration: 8-Mar-24 - 20-Aug-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Apurawan River Upstream (R/S), Aborlan, Palawan

Aporawan, Aborlan
Completed
Contractor: RITCHE-NATHALIE DEVELOPMENT CORPORATION (FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN. MERCHANDISE)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369987.88
Duration: 8-Mar-24 - 24-Jul-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Iraan River Upstream, Barangay Iraan, Aborlan, Palawan

Iraan, Aborlan
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 212295699.40
Duration: 13-Apr-23 - 7-Mar-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Iraan River Upstream, Brgy. Iraan (L/S), Aborlan, Palawan

Iraan, Aborlan
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 98999956.57
Duration: 21-May-24 - 5-Nov-24
0.0 (0)
Project Image

Construction of Flood Control Structure along Tulariquin River (RS), Roxas, Palawan

Nicanor Zabala, Roxas
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / F.F. GALANG CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 48249914.40
Duration: 20-May-24 - 11-Dec-24
0.0 (0)
Project Image

Construction of Flood Control Structure, Barangay Maoyon, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: PALBIC CONSTRUCTION AND SUPPLY
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 4899590.00
Duration: 15-Feb-23 - 5-May-23
0.0 (0)
Project Image

Construction of Flood Control Strucurue along Langogan River Downstream (LS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: AZARRAGA CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369992.99
Duration: 23-Feb-24 - 19-Jul-24
0.0 (0)
Project Image

Construction of Flood Control Strucurue along Langogan River Downstream (RS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: TAGUSAO CONSTRUCTION & TRADING INC. (FORMERLY: TAGUSAO CONSTRUCTION & TRADING)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17370000.00
Duration: 15-Feb-24 - 13-Sep-24
0.0 (0)
Project Image

Construction of Flood Control Strucurue along Langogan River Upstream (LS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: MAINTIN CONSTRUCTION & SUPPLY
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369997.40
Duration: 15-Feb-24 - 17-Sep-24
0.0 (0)
Project Image

Construction of Flood Control Strucuruealong Langogan River Upstream (RS), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: LOUIESE TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 16120415.26
Duration: 23-Feb-24 - 25-Jun-24
0.0 (0)
Project Image

Construction of Flood Control, Sitio Butterfly, Barangay Quinlogan, Quezon, Palawan

Quinlogan, Quezon
Completed
Contractor: DIANE CONSTRUCTION & ENTERPRISES
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 24499188.00
Duration: 14-Feb-24 - 15-Aug-24
0.0 (0)
Project Image

Construction of Flood Mitigation Structure and Drainage Systems Phase I, Puerto Princesa North Road, Barangay San Manuel to Outfall, Sta. 0+000 - Sta. 0+556.40, Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 96496299.03
Duration: 6-Jul-22 - 20-Dec-23
0.0 (0)
Project Image

Construction of Flood Mitigation Structure, Iraan River Waterways Phase 3, Left Bank Sta. 0+000 - Sta. 0+380, Right Bank Sta. 0+107 - Sta. 0+364, Upper Left Bank Sta. 0+389 - Sta. 0+503, Aborlan, Palawan

Iraan, Aborlan
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 96496704.82
Duration: 23-May-22 - 15-Jul-23
0.0 (0)
Project Image

Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 229.02, Coron, Palawan

Guadalupe, Coron
Completed
Contractor: JRMX CONSTRUCTION & GENERAL MERCHANDISE
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 20088519.55
Duration: 31-May-23 - 1-Oct-24
0.0 (0)
Project Image

Construction of Lamikan River Flood Control Structure, Quezon, Palawan

Tagusao, Quezon
Completed
Contractor: CUTTING EDGE BUILDERS AND TRADING, INC.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 29399992.50
Duration: 14-Feb-24 - 17-Jun-24
0.0 (0)
Project Image

Construction of Lamoro Bridge III Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 080.85, El Nido, Palawan

Pasadeña, El Nido (Bacuit)
Completed
Contractor: 12-30 CONSTRUCTION AND SUPPLY
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 8929075.23
Duration: 18-Apr-23 - 8-Dec-23
0.0 (0)
Project Image

Construction of Lanadio Flood Control Structure, Sta. 0 + 410 - Sta. 0 + 910 B/S Upstream, Barangay Barong-Barong, Brooke'S Point, Palawan

Barong-Barong, Brooke'S Point
Completed
Contractor: PTK GROUP INC.
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 44097967.76
Duration: 15-Feb-23 - 15-Oct-23
0.0 (0)
Project Image

Construction of Lanadio Flood Control Structure, Sta. 0+000 - Sta. 0+760, Brooke's Point, Palawan

Barong-Barong, Brooke'S Point
Completed
Contractor: M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 20226888.84
Duration: 25-May-22 - 7-Nov-23
0.0 (0)
Project Image

Construction of Magsarongsong Bridge Flood Control Structure, Sta. 0 + 000.00 - Sta. 0 + 084.00, Bank I UPSTREAM (L/S), Sta. 0 + 000.00 - Sta. 0 + 084.00, BANK II UPSTREAM (L/S), Roxas, Palawan

Magara (Arasan), Roxas
Completed
Contractor: PANAAD CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 9014282.42
Duration: 18-Apr-23 - 12-Sep-23
0.0 (0)
Project Image

Construction of Malatgao River Flood Control Structure, Sta. 0+000 - Sta. 0+094 Left Riverbank, Sta. 0+020 - Sta. 0+094 Right Riverbank, Quezon, Palawan

Malatgao, Quezon
Completed
Contractor: R NARRAZID TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 5504750.70
Duration: 25-May-22 - 31-Dec-23
0.0 (0)
Project Image

Construction of Malatgao Seaside Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 300 L/S Downstream, Barangay Malatgao, Narra, Palawan

Malatgao, Narra
Completed
Contractor: SAMURAI CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 21653583.72
Duration: 16-Jun-23 - 10-Feb-24
0.0 (0)
Project Image

Construction of Malinao River Flood Control Structure, Sta. 0+000 - Sta. 0+234 Right Bank, Sta. 0+040 - Sta. 0+240 Left Bank, Narra, Palawan

Malinao, Narra
Completed
Contractor: R NARRAZID TRADING AND CONSTRUCTION / RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 28986147.77
Duration: 3-Jul-22 - 31-May-23
0.0 (0)
Project Image

Construction of Mambalot CIS Drainage Canal and Slope Protection, Brooke's Point, Palawan

Mambalot, Brooke'S Point
Completed
Contractor: ALMRIN BUILDERS CORPORATION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17963797.88
Duration: 14-Feb-24 - 30-Sep-24
0.0 (0)
Project Image

Construction of Marangas River Flood Control Structure, Sta. 0+800 - Sta. 1+250, Left Bank Sta. 1+080 - Sta. 1+240, Bataraza, Palawan

Marangas (Pob.), Bataraza
Completed
Contractor: L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 28801312.60
Duration: 25-May-22 - 15-Apr-23
0.0 (0)
Project Image

Construction of Narra Poblacion Flood Control, Sta. 0+000 - Sta. 1+790, Narra, Palawan

Narra (Pob.), Narra
Completed
Contractor: C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 39324618.90
Duration: 25-May-22 - 31-Aug-23
0.0 (0)
Project Image

Construction of Panacan River Flood Control Structure, Narra, Palawan

Panacan, Narra
Completed
Contractor: C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 53063470.45
Duration: 14-Feb-24 - 15-Nov-24
0.0 (0)
Project Image

Construction of Panacan River Flood Control Structure, Sta. 0 + 070 - Sta. 0 + 770 R/S Upstream, Barangay Poblacion, Narra, Palawan

Narra (Pob.), Narra
Completed
Contractor: C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 50418886.99
Duration: 20-Feb-23 - 1-Sep-24
0.0 (0)
Project Image

Construction of Panacan Seawall, Brgy. Panacan, Municipality of Narra, Palawan

Panacan, Narra
Completed
Contractor: MEGA TAM SUMMIT INCORPORATED
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 19550848.57
Duration: 29-Mar-23 - 31-Aug-23
0.0 (0)
Project Image

Construction of Panacan Seawall, Brgy. Panacan, Narra, Palawan

Panacan, Narra
Completed
Contractor: SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 29399879.54
Duration: 21-Feb-22 - 10-Oct-22
0.0 (0)
Project Image

Construction of Panitian River Flood Control Structure, Sta. 0 + 131 - Sta. 0 + 280 B/S Downstream, Barangay Panitian, Quezon, Palawan

Panitian, Quezon
Completed
Contractor: RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 24499242.58
Duration: 23-Mar-23 - 15-Dec-23
0.0 (0)
Project Image

Construction of Panitian River Flood Control Structure, Sta. 0+000 - Sta. 0+131, Quezon, Palawan

Panitian, Quezon
Completed
Contractor: M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 11892174.24
Duration: 25-May-22 - 10-Apr-23
0.0 (0)
Project Image

Construction of Poblacion Balabac Seawall, Sta. 0+000 - Sta. 0+100, Balabac, Palawan

Poblacion III, Balabac
Completed
Contractor: ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION)
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 9328616.52
Duration: 25-Mar-22 - 2-Dec-22
0.0 (0)
Project Image

Construction of Ransang River Flood Control Structure, Rizal, Palawan

Ransang, Rizal (Marcos)
Completed
Contractor: ST. TIMOTHY CONSTRUCTION CORPORATION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 48997260.00
Duration: 14-Feb-24 - 11-Oct-24
0.0 (0)
Project Image

Construction of Ransang River Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 300 R/S Upstream, Barangay Ransang, Rizal, Palawan

Ransang, Rizal (Marcos)
Completed
Contractor: L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 24499994.74
Duration: 15-Feb-23 - 7-Dec-23
0.0 (0)
Project Image

Construction of River Bank Protection Structure along Irawan River Upstream, Barangay Irawan, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 194927222.80
Duration: 9-Mar-24 - 5-Dec-24
0.0 (0)
Project Image

Construction of River Bank Protection Works along Bulalacao River, Bataraza, Palawan

Bulalacao, Bataraza
Completed
Contractor: KATHA BUILDERS & SUPPLIES INC. / RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 192997857.40
Duration: 11-Mar-23 - 31-May-24
0.0 (0)
Project Image

Construction of River Bank Protection Works along Culandanum River, Bataraza, Palawan

Culandanum, Bataraza
Completed
Contractor: ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 192997113.10
Duration: 11-Mar-23 - 20-Aug-24
0.0 (0)
Project Image

Construction of River Waterway Enhancement Structure along Irawan River Downstream (L/S), Barangay Irawan, Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: MGB CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369990.32
Duration: 15-Feb-24 - 12-Jul-24
0.0 (0)
Project Image

Construction of River Waterway Enhancement Structure along Irawan River Downstream (R/S), Barangay Irawan, Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: MACASAET BUILDERS AND TRADING
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369942.66
Duration: 8-Mar-24 - 22-Jul-24
0.0 (0)
Project Image

Construction of River Waterway Enhancement Structure along Irawan River Upstream (R/S), Barangay Irawan, Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 17369970.05
Duration: 15-Feb-24 - 12-Jul-24
0.0 (0)
Project Image

Construction of Riverbank Protection Structures - Ransang River (Both sides) with Steel Piles, Rizal, Palawan

Ransang, Rizal (Marcos)
Completed
Contractor: ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 192997879.70
Duration: 29-Apr-23 - 22-Apr-24
0.0 (0)
Project Image

Construction of Riverbank Protection Structures - RC Dike with Steel Sheet Piles along Panacan River (Both Sides), Narra, Palawan

Panacan, Narra
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 96497566.17
Duration: 11-Mar-23 - 16-Jan-24
0.0 (0)
Project Image

Construction of Riverbank Protection Structures - RC Dike with Steel Sheet Piles along Salogon River (Both Sides), Brooks Point, Palawan

Salogon, Brooke'S Point
Completed
Contractor: HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 96497913.06
Duration: 11-Mar-23 - 21-Jan-24
0.0 (0)
Project Image

Construction of Road Dike/Esplanade along Tigaplan River, Barangay Pangobilian, Brooke's Point, Palawan

Pangobilian, Brooke'S Point
Completed
Contractor: MARCBILT CONSTRUCTION, INC.
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 192991970.00
Duration: 13-Apr-23 - 5-Mar-24
0.0 (0)
Project Image

Construction of Salogon River Flood Control Structure, Brooke's Point, Palawan

Salogon, Brooke'S Point
Completed
Contractor: SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 48995638.54
Duration: 14-Feb-24 - 15-Jul-24
0.0 (0)
Project Image

Construction of Salogon River Flood Control Structure, Sta. 0+000 - Sta. 0+520 Right Bank, Sta. 0+360 - Sta. 0+480 Left Bank, Brooke's Point, Palawan

Salogon, Brooke'S Point
Completed
Contractor: L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 39199997.00
Duration: 25-May-22 - 23-Jan-23
0.0 (0)
Project Image

Construction of Salogon River Flood Control Structure, Sta. 0+520 - Sta. 1+080 R/S Downstream, Sta. 0+480 - Sta. 0+620 L/S Downstream, Barangay Salogon, Brooke'S Point, Palawan

Salogon, Brooke'S Point
Completed
Contractor: L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source: General Appropriations Act FY 2023
Project Cost: ₱ 50657737.68
Duration: 20-Feb-23 - 25-Aug-23
0.0 (0)
Project Image

Construction of Salongsong River Flood Control Structure, Rizal, Palawan

Iraan, Rizal (Marcos)
Completed
Contractor: L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 29396659.04
Duration: 15-Mar-24 - 3-Oct-24
0.0 (0)
Project Image

Construction of Sea Wall, Barangay Caramay, Roxas, Palawan

Caramay, Roxas
Completed
Contractor: A.P. CONSEBIDO CONSTRUCTION AND TRADING
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 4949962.82
Duration: 17-Feb-22 - 29-Jul-22
0.0 (0)
Project Image

Construction of Slope Protection Structure along Balite Bridge, Taytay, Palawan

Libertad, Taytay
Completed
Contractor: JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 96499967.12
Duration: 14-Feb-24 - 27-Aug-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Iraan Bridge, Roxas, Palawan

Iraan, Roxas
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / SEVEN DIGIT CONSTRUCTION AND TRUCKING SERVICES CORP. (FORMERLY: SEVEN DIGIT CONSTRUCTION & SUPPLIES)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 44097536.12
Duration: 14-Feb-24 - 15-Oct-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Labangan Bridge 1, Coron, Palawan

Guadalupe, Coron
Completed
Contractor: ALPHA VECTOR CONSTRUCTION AND SUPPLY / JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 44098571.94
Duration: 14-Feb-24 - 21-Aug-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Lamoro Bridge 1, El Nido, Palawan

Villa Libertad, El Nido (Bacuit)
Completed
Contractor: AR LUSTRE CONSTRUCTION CORPORATION (FORMERLY:A.R. LUSTRE JR. CONSTRUCTION) / A.R.L. CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 44097774.54
Duration: 14-Feb-24 - 19-Nov-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Nagbaril Bridge 1, Coron, Palawan

Bintuan, Coron
Completed
Contractor: L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION) / ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 44079742.82
Duration: 14-Feb-24 - 26-Jul-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Tagumpay Bridge, Roxas, Palawan

Tagumpay, Roxas
Completed
Contractor: YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / SEVEN DIGIT CONSTRUCTION AND TRUCKING SERVICES CORP. (FORMERLY: SEVEN DIGIT CONSTRUCTION & SUPPLIES)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 44095477.55
Duration: 14-Feb-24 - 15-Oct-24
0.0 (0)
Project Image

Construction of Slope Protection Structure along Talog Bridge, Taytay, Palawan

Talog, Taytay
Completed
Contractor: JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 96499998.63
Duration: 14-Feb-24 - 20-Sep-24
0.0 (0)
Project Image

Construction of Slope Protection Structure, Inagawan CIS, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: KRATOS STRUCPRIME CONSTRUCTION AND SUPPLY CORP
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 14669999.48
Duration: 5-Feb-25 - 19-May-25
0.0 (0)
Project Image

Construction of Tagusao River Flood Control Structure, Sta. 0+000 - Sta. 0+200, Brooke's Point, Palawan

Barong-Barong, Brooke'S Point
Completed
Contractor: IVY MICHELLE CONSTRUCTION AND TRADING INC. (FORMERLY:IVY MICHELLE TRADING & CONTRUCTION) / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 39199918.59
Duration: 21-Mar-22 - 6-Jul-23
0.0 (0)
Project Image

Construction of Tagusao River Flood Control Structure, Sta. 0+070 - Sta. 0+620 Right Riverbank, Quezon, Palawan

Tagusao, Quezon
Completed
Contractor: L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 17279673.78
Duration: 25-May-22 - 23-May-23
0.0 (0)
Project Image

Construction of Tanabag River Waterway, (Upstream Rightside), Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: OCTAGON CONCRETE SOLUTIONS INC. / MAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 154395357.90
Duration: 9-Mar-24 - 5-Sep-24
0.0 (0)
Project Image

Construction of Taritien Flood Control Structure, Sta. 0+000 - Sta. 0+300, Narra, Palawan

Taritien, Narra
Completed
Contractor: ALMRIN BUILDERS CORPORATION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 21749296.29
Duration: 25-Mar-22 - 20-Dec-22
0.0 (0)
Project Image

Construction of Tigaplan River Flood Control Structure, Pangobilian, Brooke's Point, Palawan

Pangobilian, Brooke'S Point
Completed
Contractor: SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 53068367.03
Duration: 14-Feb-24 - 15-Oct-24
0.0 (0)
Project Image

Construction of Tumarbong River Flood Control Structure, Sta. 0+000 - Sta. 0+150, Quezon, Palawan

Maasin, Quezon
Completed
Contractor: R NARRAZID TRADING AND CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 5210917.61
Duration: 21-Feb-22 - 2-Feb-25
0.0 (0)
Project Image

Construction/Improvement of Storm Drainage System at Purok Zambales, Brgy. 3, Roxas, Palawan

Barangay III (Pob.), Roxas
Completed
Contractor: M.G.M. CONSTRUCTION
Fund Source: General Appropriations Act FY 2024
Project Cost: ₱ 9784647.85
Duration: 18-Mar-24 - 20-Dec-24
0.0 (0)
Project Image

Drainage construction at Barangay Kalipay, City of Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: N. SALES CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 4205703.56
Duration: 7-Apr-22 - 4-Nov-22
0.0 (0)
Project Image

Drainage construction at Pineda Road, Barangay San Pedro, City of Puerto Princesa, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Completed
Contractor: F.F. GALANG CONSTRUCTION
Fund Source: General Appropriations Act FY 2022
Project Cost: ₱ 4359361.95
Duration: 7-Apr-22 - 9-Dec-22
0.0 (0)
Project Image

Construction of Colby River Flood Control Structure, Rizal, Palawan

Taburi, Rizal (Marcos)
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 20000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Control Structure along Iraan River Downstream, Brgy. Poblacion, Aborlan, Palawan

Poblacion, Aborlan
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 50000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Control Structure, Iwahig River, Barangay Iwahig, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 75051000.00
Duration: Not available - Not Available
3.5 (4)
Project Image

Construction of Flood Control Structure, San Rafael River, Barangay San Rafael, Puerto Princesa City, Palawan

Iwahig (Pob.), Puerto Princesa City (Capital)
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 50000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Control Structure, Tagumpay River (Upstream), Roxas, Palawan

Tagumpay, Roxas
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 125000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Mitigation Structure, Barangay Malaking Ilog, Balabac, Palawan

Malaking Ilog, Balabac
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 40000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Mitigation Structure, Barangay Malatgao, Narra, Palawan

Malatgao, Narra
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 35000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Flood Mitigation Structure, Batang-Batang River, Narra, Palawan

Batang-Batang, Narra
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 250000000.00
Duration: Not available - Not Available
4.5 (2)
Project Image

Construction of Lubgob River Flood Control Structure, Quezon, Palawan

Alfonso XIII (Pob.), Quezon
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 43497000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Malinao River Flood Control Structure, Narra, Palawan

Malinao, Narra
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 40000000.00
Duration: Not available - Not Available
0.0 (0)
Project Image

Construction of Quinlogan River Flood Control Structure, Quezon, Palawan

Quinlogan, Quezon
Not Yet Started
Contractor: No Data Available
Fund Source: General Appropriations Act FY 2025
Project Cost: ₱ 30000000.00
Duration: Not available - Not Available
0.0 (0)