Construction of Abo-Abo River Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 200 B/S Upstream, Barangay Abo-Abo, Sofronio Española, Palawan
Abo-Abo,
Sofronio Española
Completed
Contractor:
CUTTING EDGE BUILDERS AND TRADING, INC.
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 24499265.29
Duration:
15-Feb-23 -
19-Jul-23
Construction of Abongan CIS Drainage Canal, Taytay, Palawan
Abongan,
Taytay
Completed
Contractor:
REINASTAR TRADING AND CONSTRUCTION SUPPLY
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 19598517.10
Duration:
14-Feb-24 -
28-Oct-24
Construction of Aborlan River Waterway, (Downstream Leftside) Aborlan, Palawan
Tagpait,
Aborlan
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 154398410.80
Duration:
2-Mar-24 -
5-Dec-24
Construction of Aborlan River Waterway, Puerto Princesa South Road, Aborlan, Palawan
Gogognan,
Aborlan
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 120268876.00
Duration:
11-Mar-23 -
10-Dec-23
Construction of Aramaywan River Flood Control Structure, Aramaywan, Quezon, Palawan
Aramaywan,
Quezon
Completed
Contractor:
RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 29303558.24
Duration:
14-Feb-24 -
27-Jul-24
Construction of Babuyan River Flood Control Strucure Downstream (LS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
G. BANZ BUILDERS CORP.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17029313.08
Duration:
23-Feb-24 -
24-Jun-24
Construction of Babuyan River Flood Control Strucure Downstream (RS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
AZARRAGA CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17961569.07
Duration:
15-Feb-24 -
23-May-24
Construction of Babuyan River Flood Control Strucure Upstream (LS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
F.F. GALANG CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 16802607.63
Duration:
23-Feb-24 -
24-Jul-24
Construction of Babuyan River Flood Control Strucure Upstream (RS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
PANAAD CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 18334889.53
Duration:
15-Feb-24 -
17-Jul-24
Construction of Barong-barong Flood Control Structure, Sta. 0+500 - Sta. 0+745, Brooke's Point, Palawan
Barong-barong,
Brooke'S Point
Completed
Contractor:
M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 11674127.13
Duration:
25-May-22 -
31-Jul-23
Construction of Batang Batang River Flood Control Structure, Sta 0 + 200 - Sta. 0 + 900 L/S Downstream, Barangay Batang-Batang, Narra, Palawan
Batang-Batang,
Narra
Completed
Contractor:
ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY)
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 50662496.45
Duration:
20-Feb-23 -
22-Dec-23
Construction of Batang-batang River Flood Control Structure, Narra, Palawan
Batang-batang,
Narra
Completed
Contractor:
ORANI CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY:ORANI BUILDERS & SUPPLY)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 53004257.50
Duration:
14-Feb-24 -
16-Sep-24
Construction of Bato Bridge Flood Control Structure, Taytay, Palawan
Bato,
Taytay
Completed
Contractor:
MAC BUILDERS CIVIL ENGINEERING CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 9064029.80
Duration:
15-Mar-23 -
23-Oct-23
Construction of Box Culvert in Sitios Sarimog and Pulangi, Latud, Rizal, Palawan
Latud,
Rizal (Marcos)
Completed
Contractor:
RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 9652747.12
Duration:
15-Feb-23 -
7-Oct-24
Construction of Brooke's Point Shore Protection and Causeway Development, District I, Palawan
Poblacion I,
Brooke'S Point
Completed
Contractor:
MARCBILT CONSTRUCTION, INC.
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 45816740.98
Duration:
13-Apr-23 -
30-Sep-23
Construction of Buluang Bridge I Flood Control Structure, Sta. 0 + 044.64 - Sta. 0 + 095.00 (UPSTREAM - BK.I), Sta. 0 + 000 - Sta. 0 + 095.00 (UPSTREAM - BK. II), Sta. 0 + 000.00 - Sta. 0 + 026.00 (DOWNSTREASM - BK. II), Busuanga, Palawan
Buluang,
Busuanga
Completed
Contractor:
MAC BUILDERS CIVIL ENGINEERING CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 8884656.00
Duration:
18-Apr-23 -
11-Aug-23
Construction of Cabuluan River Flood Structure, barangay Calategas, Narra, Palawan
Calategas,
Narra
Completed
Contractor:
ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 192997354.30
Duration:
13-Apr-23 -
20-May-24
Construction of Colby River Flood Control Structure, Rizal, Palawan
Taburi,
Rizal (Marcos)
Completed
Contractor:
SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 53072829.34
Duration:
14-Feb-24 -
15-Nov-24
Construction of Colby River Flood Control Structure, Sta. 0 + 620 - Sta. 0 + 820 R/S Upstream, Barangay Taburi, Rizal, Palawan
Taburi,
Rizal (Marcos)
Completed
Contractor:
SAMURAI CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 19599689.79
Duration:
3-May-23 -
15-Dec-23
Construction of Culasian Flood Control Structure, Sta. 0 + 082 - Sta. 0 + 162 R/S Downstream, Barangay Culasian, Rizal, Palawan
Culasian,
Rizal (Marcos)
Completed
Contractor:
F A M E CONSTRUCTION TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 9701996.20
Duration:
15-Feb-23 -
28-May-23
Construction of Culasian River Flood Control Structure, Sta. 0+000 - Sta. 0+082, Rizal, Palawan
Culasian,
Rizal (Marcos)
Completed
Contractor:
AFG CONSTRUCTION CORPORATION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 9653000.00
Duration:
25-May-22 -
22-Apr-23
Construction of Drainage Structure, Barangay San Miguel, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
SMMILEY BUILDERS AND TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 4900000.00
Duration:
15-Feb-23 -
27-Sep-23
Construction of Drainage System along Barangay Maligaya, City of Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
F.F. GALANG CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 4851100.32
Duration:
10-Feb-22 -
5-Jul-22
Construction of Drainage System, Tumarbong, Roxas, Palawan
Tumarbong,
Roxas
Completed
Contractor:
AFG CONSTRUCTION CORPORATION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 4514354.14
Duration:
30-Mar-23 -
29-Jun-23
Construction of Flood Control Structure along Apurawan River Downstream (L/S), Aborlan, Palawan
Aporawan,
Aborlan
Completed
Contractor:
G. BANZ BUILDERS CORP.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369994.74
Duration:
7-Mar-24 -
24-Jun-24
Construction of Flood Control Structure along Apurawan River Downstream (R/S), Aborlan, Palawan
Aporawan,
Aborlan
Completed
Contractor:
PANAAD CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 14882574.20
Duration:
23-Feb-24 -
18-Jul-24
Construction of Flood Control Structure along Apurawan River Upstream (L/S), Aborlan, Palawan
Aporawan,
Aborlan
Completed
Contractor:
RITCHE-NATHALIE DEVELOPMENT CORPORATION (FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN. MERCHANDISE)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 16240699.93
Duration:
8-Mar-24 -
20-Aug-24
Construction of Flood Control Structure along Apurawan River Upstream (R/S), Aborlan, Palawan
Aporawan,
Aborlan
Completed
Contractor:
RITCHE-NATHALIE DEVELOPMENT CORPORATION (FORMERLY: RITCHE-NATHALIE BUILDERS AND GEN. MERCHANDISE)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369987.88
Duration:
8-Mar-24 -
24-Jul-24
Construction of Flood Control Structure along Iraan River Upstream, Barangay Iraan, Aborlan, Palawan
Iraan,
Aborlan
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 212295699.40
Duration:
13-Apr-23 -
7-Mar-24
Construction of Flood Control Structure along Iraan River Upstream, Brgy. Iraan (L/S), Aborlan, Palawan
Iraan,
Aborlan
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 98999956.57
Duration:
21-May-24 -
5-Nov-24
Construction of Flood Control Structure along Tulariquin River (RS), Roxas, Palawan
Nicanor Zabala,
Roxas
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / F.F. GALANG CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 48249914.40
Duration:
20-May-24 -
11-Dec-24
Construction of Flood Control Structure, Barangay Maoyon, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
PALBIC CONSTRUCTION AND SUPPLY
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 4899590.00
Duration:
15-Feb-23 -
5-May-23
Construction of Flood Control Strucurue along Langogan River Downstream (LS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
AZARRAGA CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369992.99
Duration:
23-Feb-24 -
19-Jul-24
Construction of Flood Control Strucurue along Langogan River Downstream (RS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
TAGUSAO CONSTRUCTION & TRADING INC. (FORMERLY: TAGUSAO CONSTRUCTION & TRADING)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17370000.00
Duration:
15-Feb-24 -
13-Sep-24
Construction of Flood Control Strucurue along Langogan River Upstream (LS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
MAINTIN CONSTRUCTION & SUPPLY
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369997.40
Duration:
15-Feb-24 -
17-Sep-24
Construction of Flood Control Strucuruealong Langogan River Upstream (RS), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
LOUIESE TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 16120415.26
Duration:
23-Feb-24 -
25-Jun-24
Construction of Flood Control, Sitio Butterfly, Barangay Quinlogan, Quezon, Palawan
Quinlogan,
Quezon
Completed
Contractor:
DIANE CONSTRUCTION & ENTERPRISES
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 24499188.00
Duration:
14-Feb-24 -
15-Aug-24
Construction of Flood Mitigation Structure and Drainage Systems Phase I, Puerto Princesa North Road, Barangay San Manuel to Outfall, Sta. 0+000 - Sta. 0+556.40, Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 96496299.03
Duration:
6-Jul-22 -
20-Dec-23
Construction of Flood Mitigation Structure, Iraan River Waterways Phase 3, Left Bank Sta. 0+000 - Sta. 0+380, Right Bank Sta. 0+107 - Sta. 0+364, Upper Left Bank Sta. 0+389 - Sta. 0+503, Aborlan, Palawan
Iraan,
Aborlan
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 96496704.82
Duration:
23-May-22 -
15-Jul-23
Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 229.02, Coron, Palawan
Guadalupe,
Coron
Completed
Contractor:
JRMX CONSTRUCTION & GENERAL MERCHANDISE
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 20088519.55
Duration:
31-May-23 -
1-Oct-24
Construction of Lamikan River Flood Control Structure, Quezon, Palawan
Tagusao,
Quezon
Completed
Contractor:
CUTTING EDGE BUILDERS AND TRADING, INC.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 29399992.50
Duration:
14-Feb-24 -
17-Jun-24
Construction of Lamoro Bridge III Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 080.85, El Nido, Palawan
Pasadeña,
El Nido (Bacuit)
Completed
Contractor:
12-30 CONSTRUCTION AND SUPPLY
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 8929075.23
Duration:
18-Apr-23 -
8-Dec-23
Construction of Lanadio Flood Control Structure, Sta. 0 + 410 - Sta. 0 + 910 B/S Upstream, Barangay Barong-Barong, Brooke'S Point, Palawan
Barong-Barong,
Brooke'S Point
Completed
Contractor:
PTK GROUP INC.
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 44097967.76
Duration:
15-Feb-23 -
15-Oct-23
Construction of Lanadio Flood Control Structure, Sta. 0+000 - Sta. 0+760, Brooke's Point, Palawan
Barong-Barong,
Brooke'S Point
Completed
Contractor:
M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 20226888.84
Duration:
25-May-22 -
7-Nov-23
Construction of Magsarongsong Bridge Flood Control Structure, Sta. 0 + 000.00 - Sta. 0 + 084.00, Bank I UPSTREAM (L/S), Sta. 0 + 000.00 - Sta. 0 + 084.00, BANK II UPSTREAM (L/S), Roxas, Palawan
Magara (Arasan),
Roxas
Completed
Contractor:
PANAAD CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 9014282.42
Duration:
18-Apr-23 -
12-Sep-23
Construction of Malatgao River Flood Control Structure, Sta. 0+000 - Sta. 0+094 Left Riverbank, Sta. 0+020 - Sta. 0+094 Right Riverbank, Quezon, Palawan
Malatgao,
Quezon
Completed
Contractor:
R NARRAZID TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 5504750.70
Duration:
25-May-22 -
31-Dec-23
Construction of Malatgao Seaside Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 300 L/S Downstream, Barangay Malatgao, Narra, Palawan
Malatgao,
Narra
Completed
Contractor:
SAMURAI CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 21653583.72
Duration:
16-Jun-23 -
10-Feb-24
Construction of Malinao River Flood Control Structure, Sta. 0+000 - Sta. 0+234 Right Bank, Sta. 0+040 - Sta. 0+240 Left Bank, Narra, Palawan
Malinao,
Narra
Completed
Contractor:
R NARRAZID TRADING AND CONSTRUCTION / RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 28986147.77
Duration:
3-Jul-22 -
31-May-23
Construction of Mambalot CIS Drainage Canal and Slope Protection, Brooke's Point, Palawan
Mambalot,
Brooke'S Point
Completed
Contractor:
ALMRIN BUILDERS CORPORATION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17963797.88
Duration:
14-Feb-24 -
30-Sep-24
Construction of Marangas River Flood Control Structure, Sta. 0+800 - Sta. 1+250, Left Bank Sta. 1+080 - Sta. 1+240, Bataraza, Palawan
Marangas (Pob.),
Bataraza
Completed
Contractor:
L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 28801312.60
Duration:
25-May-22 -
15-Apr-23
Construction of Narra Poblacion Flood Control, Sta. 0+000 - Sta. 1+790, Narra, Palawan
Narra (Pob.),
Narra
Completed
Contractor:
C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 39324618.90
Duration:
25-May-22 -
31-Aug-23
Construction of Panacan River Flood Control Structure, Narra, Palawan
Panacan,
Narra
Completed
Contractor:
C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 53063470.45
Duration:
14-Feb-24 -
15-Nov-24
Construction of Panacan River Flood Control Structure, Sta. 0 + 070 - Sta. 0 + 770 R/S Upstream, Barangay Poblacion, Narra, Palawan
Narra (Pob.),
Narra
Completed
Contractor:
C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 50418886.99
Duration:
20-Feb-23 -
1-Sep-24
Construction of Panacan Seawall, Brgy. Panacan, Municipality of Narra, Palawan
Panacan,
Narra
Completed
Contractor:
MEGA TAM SUMMIT INCORPORATED
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 19550848.57
Duration:
29-Mar-23 -
31-Aug-23
Construction of Panacan Seawall, Brgy. Panacan, Narra, Palawan
Panacan,
Narra
Completed
Contractor:
SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 29399879.54
Duration:
21-Feb-22 -
10-Oct-22
Construction of Panitian River Flood Control Structure, Sta. 0 + 131 - Sta. 0 + 280 B/S Downstream, Barangay Panitian, Quezon, Palawan
Panitian,
Quezon
Completed
Contractor:
RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 24499242.58
Duration:
23-Mar-23 -
15-Dec-23
Construction of Panitian River Flood Control Structure, Sta. 0+000 - Sta. 0+131, Quezon, Palawan
Panitian,
Quezon
Completed
Contractor:
M.C. ESCALA CONSTRUCTION AND SUPPLY
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 11892174.24
Duration:
25-May-22 -
10-Apr-23
Construction of Poblacion Balabac Seawall, Sta. 0+000 - Sta. 0+100, Balabac, Palawan
Poblacion III,
Balabac
Completed
Contractor:
ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 9328616.52
Duration:
25-Mar-22 -
2-Dec-22
Construction of Ransang River Flood Control Structure, Rizal, Palawan
Ransang,
Rizal (Marcos)
Completed
Contractor:
ST. TIMOTHY CONSTRUCTION CORPORATION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 48997260.00
Duration:
14-Feb-24 -
11-Oct-24
Construction of Ransang River Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 300 R/S Upstream, Barangay Ransang, Rizal, Palawan
Ransang,
Rizal (Marcos)
Completed
Contractor:
L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 24499994.74
Duration:
15-Feb-23 -
7-Dec-23
Construction of River Bank Protection Structure along Irawan River Upstream, Barangay Irawan, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC.
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 194927222.80
Duration:
9-Mar-24 -
5-Dec-24
Construction of River Bank Protection Works along Bulalacao River, Bataraza, Palawan
Bulalacao,
Bataraza
Completed
Contractor:
KATHA BUILDERS & SUPPLIES INC. / RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 192997857.40
Duration:
11-Mar-23 -
31-May-24
Construction of River Bank Protection Works along Culandanum River, Bataraza, Palawan
Culandanum,
Bataraza
Completed
Contractor:
ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 192997113.10
Duration:
11-Mar-23 -
20-Aug-24
Construction of River Waterway Enhancement Structure along Irawan River Downstream (L/S), Barangay Irawan, Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
MGB CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369990.32
Duration:
15-Feb-24 -
12-Jul-24
Construction of River Waterway Enhancement Structure along Irawan River Downstream (R/S), Barangay Irawan, Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
MACASAET BUILDERS AND TRADING
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369942.66
Duration:
8-Mar-24 -
22-Jul-24
Construction of River Waterway Enhancement Structure along Irawan River Upstream (R/S), Barangay Irawan, Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 17369970.05
Duration:
15-Feb-24 -
12-Jul-24
Construction of Riverbank Protection Structures - Ransang River (Both sides) with Steel Piles, Rizal, Palawan
Ransang,
Rizal (Marcos)
Completed
Contractor:
ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP. / RDF TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 192997879.70
Duration:
29-Apr-23 -
22-Apr-24
Construction of Riverbank Protection Structures - RC Dike with Steel Sheet Piles along Panacan River (Both Sides), Narra, Palawan
Panacan,
Narra
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 96497566.17
Duration:
11-Mar-23 -
16-Jan-24
Construction of Riverbank Protection Structures - RC Dike with Steel Sheet Piles along Salogon River (Both Sides), Brooks Point, Palawan
Salogon,
Brooke'S Point
Completed
Contractor:
HARDROCKPLATINUM DEVELOPMENT CORPORATION / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 96497913.06
Duration:
11-Mar-23 -
21-Jan-24
Construction of Road Dike/Esplanade along Tigaplan River, Barangay Pangobilian, Brooke's Point, Palawan
Pangobilian,
Brooke'S Point
Completed
Contractor:
MARCBILT CONSTRUCTION, INC.
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 192991970.00
Duration:
13-Apr-23 -
5-Mar-24
Construction of Salogon River Flood Control Structure, Brooke's Point, Palawan
Salogon,
Brooke'S Point
Completed
Contractor:
SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 48995638.54
Duration:
14-Feb-24 -
15-Jul-24
Construction of Salogon River Flood Control Structure, Sta. 0+000 - Sta. 0+520 Right Bank, Sta. 0+360 - Sta. 0+480 Left Bank, Brooke's Point, Palawan
Salogon,
Brooke'S Point
Completed
Contractor:
L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 39199997.00
Duration:
25-May-22 -
23-Jan-23
Construction of Salogon River Flood Control Structure, Sta. 0+520 - Sta. 1+080 R/S Downstream, Sta. 0+480 - Sta. 0+620 L/S Downstream, Barangay Salogon, Brooke'S Point, Palawan
Salogon,
Brooke'S Point
Completed
Contractor:
L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2023
Project Cost:
₱ 50657737.68
Duration:
20-Feb-23 -
25-Aug-23
Construction of Salongsong River Flood Control Structure, Rizal, Palawan
Iraan,
Rizal (Marcos)
Completed
Contractor:
L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 29396659.04
Duration:
15-Mar-24 -
3-Oct-24
Construction of Sea Wall, Barangay Caramay, Roxas, Palawan
Caramay,
Roxas
Completed
Contractor:
A.P. CONSEBIDO CONSTRUCTION AND TRADING
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 4949962.82
Duration:
17-Feb-22 -
29-Jul-22
Construction of Slope Protection Structure along Balite Bridge, Taytay, Palawan
Libertad,
Taytay
Completed
Contractor:
JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 96499967.12
Duration:
14-Feb-24 -
27-Aug-24
Construction of Slope Protection Structure along Iraan Bridge, Roxas, Palawan
Iraan,
Roxas
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / SEVEN DIGIT CONSTRUCTION AND TRUCKING SERVICES CORP. (FORMERLY: SEVEN DIGIT CONSTRUCTION & SUPPLIES)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 44097536.12
Duration:
14-Feb-24 -
15-Oct-24
Construction of Slope Protection Structure along Labangan Bridge 1, Coron, Palawan
Guadalupe,
Coron
Completed
Contractor:
ALPHA VECTOR CONSTRUCTION AND SUPPLY / JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 44098571.94
Duration:
14-Feb-24 -
21-Aug-24
Construction of Slope Protection Structure along Lamoro Bridge 1, El Nido, Palawan
Villa Libertad,
El Nido (Bacuit)
Completed
Contractor:
AR LUSTRE CONSTRUCTION CORPORATION (FORMERLY:A.R. LUSTRE JR. CONSTRUCTION) / A.R.L. CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 44097774.54
Duration:
14-Feb-24 -
19-Nov-24
Construction of Slope Protection Structure along Nagbaril Bridge 1, Coron, Palawan
Bintuan,
Coron
Completed
Contractor:
L. B. LEONCIO TRADING AND CONSTRUCTION CORPORATION (FORMERLY: L.B. LEONCIO TRADING & CONSTRUCTION) / ONE HUNDRED PERCENT CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY:BCT TRADING & CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 44079742.82
Duration:
14-Feb-24 -
26-Jul-24
Construction of Slope Protection Structure along Tagumpay Bridge, Roxas, Palawan
Tagumpay,
Roxas
Completed
Contractor:
YURICH BUILDERS AND CONSTRUCTION SUPPLY INC. / SEVEN DIGIT CONSTRUCTION AND TRUCKING SERVICES CORP. (FORMERLY: SEVEN DIGIT CONSTRUCTION & SUPPLIES)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 44095477.55
Duration:
14-Feb-24 -
15-Oct-24
Construction of Slope Protection Structure along Talog Bridge, Taytay, Palawan
Talog,
Taytay
Completed
Contractor:
JASMIG CONSTRUCTION CORPORATION (FORMERLY: JASMIG CONSTRUCTION SUPPLY)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 96499998.63
Duration:
14-Feb-24 -
20-Sep-24
Construction of Slope Protection Structure, Inagawan CIS, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
KRATOS STRUCPRIME CONSTRUCTION AND SUPPLY CORP
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 14669999.48
Duration:
5-Feb-25 -
19-May-25
Construction of Tagusao River Flood Control Structure, Sta. 0+000 - Sta. 0+200, Brooke's Point, Palawan
Barong-Barong,
Brooke'S Point
Completed
Contractor:
IVY MICHELLE CONSTRUCTION AND TRADING INC. (FORMERLY:IVY MICHELLE TRADING & CONTRUCTION) / C.T. LEONCIO CONSTRUCTION & TRADING
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 39199918.59
Duration:
21-Mar-22 -
6-Jul-23
Construction of Tagusao River Flood Control Structure, Sta. 0+070 - Sta. 0+620 Right Riverbank, Quezon, Palawan
Tagusao,
Quezon
Completed
Contractor:
L&M RODRIGUEZ CONSTRUCTION AND TRADING INC. (FORMERLY: M.M. RODRIGUEZ TRADING AND CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 17279673.78
Duration:
25-May-22 -
23-May-23
Construction of Tanabag River Waterway, (Upstream Rightside), Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
OCTAGON CONCRETE SOLUTIONS INC. / MAC BUILDERS CORP. (FORMERLY: MAC BUILDERS DEVELOPMENT CORPORATION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 154395357.90
Duration:
9-Mar-24 -
5-Sep-24
Construction of Taritien Flood Control Structure, Sta. 0+000 - Sta. 0+300, Narra, Palawan
Taritien,
Narra
Completed
Contractor:
ALMRIN BUILDERS CORPORATION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 21749296.29
Duration:
25-Mar-22 -
20-Dec-22
Construction of Tigaplan River Flood Control Structure, Pangobilian, Brooke's Point, Palawan
Pangobilian,
Brooke'S Point
Completed
Contractor:
SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 53068367.03
Duration:
14-Feb-24 -
15-Oct-24
Construction of Tumarbong River Flood Control Structure, Sta. 0+000 - Sta. 0+150, Quezon, Palawan
Maasin,
Quezon
Completed
Contractor:
R NARRAZID TRADING AND CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 5210917.61
Duration:
21-Feb-22 -
2-Feb-25
Construction/Improvement of Storm Drainage System at Purok Zambales, Brgy. 3, Roxas, Palawan
Barangay III (Pob.),
Roxas
Completed
Contractor:
M.G.M. CONSTRUCTION
Fund Source:
General Appropriations Act FY 2024
Project Cost:
₱ 9784647.85
Duration:
18-Mar-24 -
20-Dec-24
Drainage construction at Barangay Kalipay, City of Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
N. SALES CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 4205703.56
Duration:
7-Apr-22 -
4-Nov-22
Drainage construction at Pineda Road, Barangay San Pedro, City of Puerto Princesa, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Completed
Contractor:
F.F. GALANG CONSTRUCTION
Fund Source:
General Appropriations Act FY 2022
Project Cost:
₱ 4359361.95
Duration:
7-Apr-22 -
9-Dec-22
Construction of Colby River Flood Control Structure, Rizal, Palawan
Taburi,
Rizal (Marcos)
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 20000000.00
Duration:
Not available -
Not Available
Construction of Flood Control Structure along Iraan River Downstream, Brgy. Poblacion, Aborlan, Palawan
Poblacion,
Aborlan
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 50000000.00
Duration:
Not available -
Not Available
Construction of Flood Control Structure, Iwahig River, Barangay Iwahig, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 75051000.00
Duration:
Not available -
Not Available
Construction of Flood Control Structure, San Rafael River, Barangay San Rafael, Puerto Princesa City, Palawan
Iwahig (Pob.),
Puerto Princesa City (Capital)
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 50000000.00
Duration:
Not available -
Not Available
Construction of Flood Control Structure, Tagumpay River (Upstream), Roxas, Palawan
Tagumpay,
Roxas
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 125000000.00
Duration:
Not available -
Not Available
Construction of Flood Mitigation Structure, Barangay Malaking Ilog, Balabac, Palawan
Malaking Ilog,
Balabac
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 40000000.00
Duration:
Not available -
Not Available
Construction of Flood Mitigation Structure, Barangay Malatgao, Narra, Palawan
Malatgao,
Narra
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 35000000.00
Duration:
Not available -
Not Available
Construction of Flood Mitigation Structure, Batang-Batang River, Narra, Palawan
Batang-Batang,
Narra
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 250000000.00
Duration:
Not available -
Not Available
Construction of Lubgob River Flood Control Structure, Quezon, Palawan
Alfonso XIII (Pob.),
Quezon
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 43497000.00
Duration:
Not available -
Not Available
Construction of Malinao River Flood Control Structure, Narra, Palawan
Malinao,
Narra
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 40000000.00
Duration:
Not available -
Not Available
Construction of Quinlogan River Flood Control Structure, Quezon, Palawan
Quinlogan,
Quezon
Not Yet Started
Contractor:
No Data Available
Fund Source:
General Appropriations Act FY 2025
Project Cost:
₱ 30000000.00
Duration:
Not available -
Not Available